The migration of mail from the temporary site back to the production server did not occur on March 16 as previously planned. The reasons for this were:
As a result of these events, the migration of mail from the temporary server back to the production server was postponed until April 6, 1997. April 6 is the earliest available date for this postponement. The quarter break downtime is still going to occur as planned.
Please refer to the April 6 Downtime Notice for additional information.
Revised by: George Westlund (gwestlun@calpoly.edu)