August 7th, 1996

Two more systems arrived (one yesterday and one today) in the machine room. From the looks of things, we are planning for a total of seven racks (six systems plus the rack containing the raid array).


Figure 1: Two new HP K420 Systems


Figure 2: Additional boxes with consoles, monitors, etc.

We are also meeting in-depth with an HP implementation team looking to what we should be able to get accomplished by the beginning of Fall quarter 1996 and in the months that follow.

Revised by: George Westlund (gwestlun@calpoly.edu)
Revised: August 7th, 1996

Back to the Main Table of Contents

Back to the Cal Poly Home Page